Site Progress

apr-2021
Vacant Possession / Site Clearance / Work Commencement
April 2021

The site is now vacant and ready for construction work to begin. Site clearance has been completed, and preparations are underway for work commencement.

may-2021
Signboard & Hoarding Installation
May 2021

Signboards and hoardings are installed to demarcate the construction site and ensure safety for workers and the public.

oct-2021
Commencement of Piling Works
October 2021

Bore pile construction is currently underway, a process that involves drilling deep holes into the ground to create a foundation for the structure.

jan-2022
Piling Works in Progress
January 2022

Bore pile construction continues to progress steadily.

April 2022 Combined
TNB Cables Diversion Works Carried Out
April 2022

The TNB cables diversion work is in progress, which involves rerouting electrical cables to accommodate the construction site.

June 2022 Combined
Piling Works Completed
June 2022

Bore pile construction has been completed, providing a solid foundation for the upcoming construction.

july-22
Diaphragm Wall Construction in Progress
July 2022

Diaphragm wall construction is now in progress. This involves constructing a wall made of interlocking concrete panels that will serve as a structural support for the building.

July 2022 Combined
Air Selangor On-Site Inspection
July 2022

Air Selangor is on-site to perform a pressure test on the existing 450mm water pipes, which were found during guide wall construction and diversion work to be carried out to make way for the construction.

September 2022 Combined
Diaphragm Wall Construction in Progress
September 2022

Diaphragm wall construction continues to progress as planned.

October 2022 Combined
Air Selangor On-Site Inspection
October 2022

An Air Selangor contractor inspects the site to ensure that all construction work is being carried out according to regulations and guidelines.

November 2022 Combined
Materials Inspection by Air Selangor
November 2022

Materials and pipes are inspected by Air Selangor to ensure that they meet the required standards and specifications.

December 2022 Combined
Water Pipes Diversion Works
December 2022

Piloting and laying of 400mm water pipes commenced, marking a significant stage in the diversion work.

January 2023 Combined
Pressure Test by Air Selangor
January 2023

Preparations are underway for a pressure test on the 400mm water pipes to ensure that they can handle the required water flow.

FEBRUARY 2023 Combined
Hot Tapping of Water Pipes
February 2023

Preparations are made for the hot tapping of the 400mm water pipes, marking a significant step towards the completion of the diversion work.

March 2022 Combined 1
Shutting Down Existing Pipes & Welding End Cap
March 2023

Preparations are made for shutting down the existing pipe and welding the end cap, marking a critical stage in the diversion work's progress.

March 2023 Combined 2
Water Pipes Diversion Works Completed
March 2023

The line stopping machine is removed, and backfilling work, installation of the chamber and marker post commences, marking the final stages of the diversion work's completion.

May 2023 Combined
Diaphragm Wall Construction in Progress
May 2023

Diaphragm wall construction continues to progress as planned.

June 2023 Combined
Diaphragm Wall Construction Completed
June 2023

With the diaphragm wall construction finished, the project has achieved a crucial element of its structural development. The completed diaphragm wall ensures that the building will have a solid and secure base to support its future construction phases.

July 2023 Combined
Driving Temporary Sheet Piles for Drainage Work
July 2023

The installation of temporary sheet piles is a critical step in the construction process, as it sets the groundwork for the subsequent phases of drainage work. These sheet piles will act as a temporary retaining wall, preventing soil erosion and maintaining the stability of the construction site.

August 2023 Combined
Commencement of Drainage Work
August 2023

Construction work continues with the commencement of drainage work, including excavation and the installation of box culverts. This phase is crucial for water management and site stability, and it's closely monitored for quality and adherence to safety standards.

September 2023 Combined
Commencement of Capping Beam Work
September 2023

A new phase of construction has commenced with the start of capping beam work. This involves the fabrication of reinforcing bars and the casting of concrete for the capping beams. Capping beams are vital structural elements that provide support and stability to the building's foundation.

November 2023 Combined
Commencement of Excavation Work
November 2023

Exciting progress unfolds as the construction site enters a new phase with the commencement of excavation work. The focus is on earthwork excavation to forming the underground basement and laying the groundwork for subsequent structural construction.

December 2023 Combined
Basement Work in Progress
December 2023

Exciting developments unfold on the construction site as the construction of the underground basement structure is well underway. The team is making steady progress, sticking to the planned timeline.

January 2024 Combined
Basement Work in Progress
January 2024
February 2024 Combined
Basement Work in Progress
February 2024
March 2024 Combined
Basement Work in Progress
March 2024
April 2024 Combined
Basement Work in Progress
April 2024
May 2024 Combined
Basement Work in Progress
May 2024
June 2024 Combined
Basement Work in Progress
June 2024
July 2024 Combined
Basement Work in Progress
July 2024
August 2024 Combined
Basement Work in Progress
August 2024

Substructure work is progressing steadily, with completion up to Basement 3. Excavation is ongoing at Basement 4, along with concurrent work on the Ground floor slab.

September 2024 Combined
Basement Work in Progress
September 2024
October 2024 Combined
Basement Work in Progress
October 2024
November 2024 Combined
Basement Work in Progress
November 2024

The project is progressing smoothly, with substructure work reaching 90% completion. The contractor is currently working on the pile caps and Basement 4 slab. Concurrently, efforts are underway to construct staircases, driving ramps for the basement, and close the openings for earthworks.

December 2024 Combined
Basement Work in Progress
December 2024
January 2025 Combined
Basement Work in Progress
January 2025

The current progress of the substructure is up to B1 driving ramps, transfer beams, and the ground floor slab.

February 2025 Combined
Basement Work in Progress
February 2025

The substructure is progressing well, with concrete casting for the ground floor slab underway. This marks a key milestone toward completing the substructure.

March 2025 Combined
Transition to Main Building Works
March 2025

The substructure was successfully completed in late February up to the ground floor slab. In early March, the Company and Consultants inspected the site, and the Main Contractor has now taken over to begin the main building works, marking the start of the superstructure phase.

April 2025 Combined
Main Building Works in Progress
April 2025

Construction is progressing smoothly, with structural works advancing up to the Mezzanine floor slab. The project remains on schedule as the main building works continue steadily.

May 2025 Combined
Main Building Works in Progress
May 2025

Construction is progressing well, with structural works advancing up to the second floor slab. Work remains on schedule as the building continues to take shape.

June 2025 Combined
Main Building Works in Progress
June 2025
July 2025 Combined
Main Building Works in Progress
July 2025
August 2025 Combined
Main Building Works in Progress
August 2025
October 2025 Combined
Main Building Works in Progress
October 2025